Bombay High Court Ruling: Arbitral Tribunal’s Obligation to Provide Reasons while dealing with Liquidated Damages

The Bombay High Court’s recent judgment in HPCL v. GR Engineering Pvt Ltd has underscored the importance of reasoned decisions in arbitration proceedings. The case involved a dispute arising from a 2006 contract between Hindustan Petroleum Corporation Limited (HPCL) and GR Engineering Pvt Ltd (GRE) for the construction of LPG mounded bullets at a refinery in Mumbai.

 

 Case Background: 

 

The contract between HPCL and GRE included provisions for liquidated damages in case of delays or breaches. When disputes arose, the matter was referred to arbitration. The arbitral tribunal ultimately denied HPCL’s claim for liquidated damages, prompting HPCL to challenge the award before the Bombay High Court.

 

 Key Pointers: 

 

–  Arbitral Tribunal’s Reasoning Obligation:  The Bombay High Court held that the arbitral tribunal is obligated to provide detailed reasons for denying liquidated damages.

–  Importance of Transparency:  The court emphasized the need for transparency and accountability in arbitral decision-making, ensuring that parties understand the basis for the tribunal’s conclusions.

 

 Implications of the Ruling: 

 

The judgment highlights the significance of providing reasoned decisions in arbitration awards. Arbitral tribunals must ensure that their decisions are well-reasoned and transparent to avoid potential challenges. This ruling serves as a reminder of the importance of detailed analysis and clear reasoning in arbitral proceedings.

 

 Key Takeaways: 

 

– Arbitral tribunals must provide clear and specific reasons for their decisions.

– Failure to provide adequate reasons may render the award vulnerable to challenge.

 

 Conclusion: 

 

The Bombay High Court’s ruling in _HPCL v. GR Engineering Pvt Ltd_ reinforces the importance of reasoned decisions in arbitration. By emphasizing the need for transparency and accountability, the court has set a clear expectation for arbitral tribunals to provide detailed and well-reasoned awards.

Recent Articles

White-Collar Crime Cases Explained: Expert Legal Guidance
White-Collar Crime
December 16, 2025
Supply Chain Due Diligence 2025: Legal Risk Management for Indian Importers & Exporters
Supply Chain Due Diligence 2025: Legal Risk Management for Indian Importers & Exporters
December 13, 2025
Family Law 2025: Handling Digital & Crypto Asset Division in Divorce Cases
Family Law 2025: Handling Digital & Crypto Asset Division in Divorce Cases
December 11, 2025

Get in Touch

At Law Chambers of Pooja Dua, we value your concerns and are here to provide prompt, professional legal assistance. Whether you’re seeking expert guidance or need representation, we’re just a call or message away.

📍 Office Address
11th Floor, Arunachal Complex, 1117-1120, Barakhamba Rd, Connaught Place, New Delhi, Delhi 110001

📞 Phone: +91 7838515821
📧 Email: info@lawchambersofpoojadua.com

Disclaimer & Confirmation

As per the rules of the Bar Council of India, we are not permitted to solicit work and advertise. By clicking on the “Accept” button below, the user acknowledges the following:

• There has been no advertisement, personal communication, solicitation, invitation, or inducement of any sort whatsoever from us or any of our members to solicit any work through this website.
• The user wishes to gain more information about us for his/her own information and use.
• The information about us is provided to the user only on his/her specific request and any information obtained or materials downloaded from this website is completely at the user’s volition and any transmission, receipt or use of this site would not create any lawyer-client relationship.
• The information provided under this website is solely available at your request for informational purposes only and should not be interpreted as soliciting or advertisement.
• We are not liable for any consequence of any action taken by the user relying on material/information provided under this website. In cases where the user has any legal issues, he/she in all cases must seek independent legal advice, as the material contained in this document does not constitute/substitute professional advice that may be required before acting on any matter. Neither this website nor the web pages and the information contained herein constitute a contract or will form the basis of a contract. While every care has been taken in preparing the content of this website and web pages to ensure accuracy at the time of publication and creation, however, Law Chambers Of Pooja Dua assumes no responsibility for any errors, which despite all precautions may be found herein. All disputes, if any, are subject to the exclusive jurisdiction of courts at New Delhi, India only.